LogoLogo
Hub HomeDownloadsDocumentationReleases
  • Welcome
  • Introduction to HOLOPLOT
    • HOLOPLOT unique capabilities
    • HOLOPLOT technology
    • HOLOPLOT OS
      • Audio signal flow
    • Product family
  • user guides
    • HOLOPLOT system design
      • System design best practices
        • Introduction to sound system design
        • Which HOLOPLOT product is best suited to the application?
        • How do I decide on the position of my arrays?
        • What should be the size and aspect ratio of my arrays?
      • Beam design best practices
        • What are the fundamental principles of designing with beams?
        • How do I set up my coverage zones and what impact does that have on my design?
        • What are the different beam parameters and how do I apply them in my design?
        • How do I apply those beams in real world applications?
    • HOLOPLOT system deployment
      • Integration overview
      • Unboxing
      • Networking overview
      • AES67 Quick start guide
      • Advanced Network Configuration Tips
      • Power
      • Rigging
        • X1 Rigging Components
        • X1 standard rigging side plate attachment guide
        • X1 Standard rigging lifting procedures
        • X1 custom rigging
      • Venue validation
      • System operation & monitoring
      • Pairing the arrays & routing audio
      • Align and tune beams
      • Measurement and system optimization
    • Troubleshooting
  • HOLOPLOT Plan
    • Getting started
      • Recommended specifications
      • Installing HOLOPLOT Plan
      • Additional 3rd party tools
      • Navigating the interface
    • Onboarding videos
    • Importing 3D assets from SketchUp
      • Setting up the SketchUp toolkit
      • Installing the Khronos glTF Exporter for SketchUp
      • Defining zone types in SketchUp
      • Importing assets from SketchUp
    • Working with Matrix Arrays
      • Creating arrays
      • Moving arrays
    • Working with zones
      • Defining zone types
      • Drawing zones
      • Moving zones
    • Working with presets
      • Creating a preset
      • Working with preset layers
      • Working with environmental conditions
    • Working with beams
      • Creating a Parametric Beam
        • Adjusting Parametric Beam parameters
      • Creating a Virtual Source
        • Adjusting Virtual Source parameters
      • Creating a Coverage Beam
        • Assigning zones to a Coverage Beam
        • Adjusting Coverage Beam parameters
        • Optimizing a Coverage Beam
        • Working with beam variants (advanced)
      • Creating an LF Coverage Beam
        • Creating crossovers
      • Routing Beams
    • Simulation
      • Simulation controls
      • Tuning
      • Probe Mode
      • Simulating with S21 arrays
    • Saving & exporting
      • Exporting to AFMG EASE
  • HOLOPLOT Control
    • Getting started
      • Accessing HOLOPLOT Control
      • Navigating the interface
    • Configuring the system
      • Setting up system essentials
      • Managing a project
      • Pairing Modules
      • Network Settings - RAVENNA only
      • Stream Management - RAVENNA only
      • Setting up Analog mode on X2 Modules
    • Operating the system
      • Getting an overview of the active project
      • Routing streams to audio inputs
      • Switching presets and environmental conditions
      • Applying actions to the system
      • Tuning beams
      • Monitoring level meters
    • Maintaining the system
      • Monitoring device health
      • Module driver test
      • Module and Controller events
      • Module and Controllers Issues List
  • HOLOPLOT API
    • Getting started
    • Documentation
      • Arrays and modules
      • Beams and presets
      • Device health
      • Controllers
      • System operation
      • Spaces
    • Examples
      • Changing a preset
      • Adjusting the system's gain
Powered by GitBook
On this page
  • Parts naming convention
  • Module locking features
  • 1. Attachment
  • 2. Mechanism detail
  • 3. Connection modules
  • 4. Hole details
  • 5. Attachment of lift bars
  • 6. Attachment of 2nd lift bar
  • 7. Lifting up upper modules
  • 8. Vertical connection

Was this helpful?

Export as PDF
  1. user guides
  2. HOLOPLOT system deployment
  3. Rigging

X1 Standard rigging lifting procedures

PreviousX1 standard rigging side plate attachment guideNextX1 custom rigging

Last updated 10 months ago

Was this helpful?

LogoLogo

HOLOPLOT

  • HOLOPLOT Website
  • Contact
  • Imprint
  • Privacy Policy

© 2024 HOLOPLOT GmbH. All rights reserved.

This document is a non-comprehensive visual guide that contains images, text, and video with HOLOPLOT’s X1 rigging system in motion.

This document is an overview of the rigging operation procedures for discussion or presentation purposes.

This document does not contain sufficient information in order to safely or successfully operate HOLOPLOT’s X1 Rigging system.

DO NOT operate HOLOPLOT X1 rigging without fully reading and comprehending the HOLOPLOT X1 Rigging Manual.

Email support@holoplot.com if you need the HOLOPLOT X1 Rigging Manual

Parts naming convention

  1. X1 Liftbar

  2. X1 Lift plate Left

  3. X1 Lift plate Right

  4. X1 Side plate Left

  5. X1 Side plate Right

  6. MD96

Module locking features

  1. Main lever

  2. Lever release

  3. Side lever

  4. Side connector

  5. Hook bar

1. Attachment

Step 1

Press down on the lever release

Step 2

Lift the main lever upward

Step 3

Insert X1 lift plates onto the top of side plates (into hookbar slots)

Step 4

Push the main lever downward

2. Mechanism detail

3. Connection modules

Step 1

Open the lid of the Dolly Cases

Bring the side Dolly Bumper-Flaps down

Step 2

Lift up on the side lever

Step 3

Push the Audio Modules together

Step 4

Press down the side lever

Wheel boards or flight cases can be used to replace the dollies during installation. The wheel board can not be wider than 80 cm max, and need to be able to take a load of up to 190 kg.

All wheel boards need to have exactly the same height so modules can be interconnected horizontally.

After placing the module (with rigging attached) on a wheelboard with the sideplates hanging over left & right follow step 3-5 from previous page.

4. Hole details

5. Attachment of lift bars

Step 1

Insert lift bar into lift plate rails

Step 2

Remove the lift bar QRPs from their storage position

Step 3

Insert them into the hole number you want to use

Step 4

Verify that the QRPs have been inserted into the same hole number on both lift plates (left and right)

6. Attachment of 2nd lift bar

Step 1

Insert lift bar into lift plate rails

Step 2

Remove the lift bar QRPs from their storage position

Step 3

Insert them into hole number you want to use and insert the pin also in neighboring lift bar

Step 4

Verify that the QRPs have been inserted into the same hole number on both lift plates (left and right)

7. Lifting up upper modules

Step 1

Check lift bar secure connection

Step 2

Insert shackle and secure the connection to the lift bar

Step 3

Make sure the dolly locks are first opened

Step 4

Lift the array up

8. Vertical connection

Step 1

Open all four main levers of the connecting modules

Step 2

Slowly bring the flown array down and guide the feet of the bottom module

Step 3

Close all four main levers to secure the two groups of modules together

Step 4

Make sure the dolly locks are first opened, then lift the array up

Lift the array